FORCAM
Case Studies
GKN Aerospace Achieves 20% Reduction in Operation Time with FORCAM FORCE
Overview
GKN Aerospace Achieves 20% Reduction in Operation Time with FORCAM FORCEFORCAM |
Functional Applications - Manufacturing Execution Systems (MES) Analytics & Modeling - Predictive Analytics Application Infrastructure & Middleware - Data Visualization | |
Aerospace | |
Process Manufacturing Maintenance Quality Assurance | |
Machine Condition Monitoring Predictive Maintenance Energy Management System Process Control & Optimization Real-Time Location System (RTLS) | |
System Integration Data Science Services Training | |
Operational Impact
GKN Aerospace achieved a 20% reduction in operation time, leading to increased direct labor efficiency and on-time delivery. | |
The implementation of FORCAM FORCE allowed for better machine utilization and cost reduction. | |
The visual lean manufacturing environment provided by FORCAM FORCE enabled operators to signal line status and react promptly to issues, improving overall equipment efficiency (OEE). | |
Quantitative Benefit
20% reduction in operation time | |
Lead time reduced from 50 days to 34 days | |