ICONICS Case Studies Customer Success Story: Kazakhstan Railway
Edit This Case Study Record
ICONICS Logo

Customer Success Story: Kazakhstan Railway

ICONICS
Application Infrastructure & Middleware - Data Exchange & Integration
Networks & Connectivity - Ethernet
Railway & Metro
Logistics & Transportation
Maintenance
Energy Management System
Remote Asset Management
System Integration
Kazakhstan’s railways, incorporated into JSC National Company Kazakhstan Temir Zholy (KTZ), combines about 14,000 kilometers of rails with 700 stations. The amount of cargo and passenger traffic grows every year, inevitably leading to higher electricity expenditures. Electricity usage reform and increasing prices for energy resource are common everywhere. Therefore, implementation of an Automation System of Control and consumption for Energy (ASCUE) for the rail node was seen as a necessity. The railways need the system for real-time electricity monitoring to minimize energy use and ensure an optimum relationship between costs and the volume of work and services.
Read More
Kazakhstan’s railways celebrated their centennial in 2004. The state rail facilities have been incorporated into JSC National Company Kazakhstan Temir Zholy (KTZ) more than ten years ago. Kazakhstan’s railroad combines about 14,000 kilometers of rails with 700 stations and KTZ is one of the railways reform leaders in the Commonwealth of Independent States (CIS). According to KTZ’s mission statement, the company works to ensure the “effective organization, coordination and maintenance of transportation processes with the purpose of the maximal satisfaction of needs of freight senders and the population at rational use of resources”.
Read More
The system integrator Technik-Trade, a PROSOFT company dealer in Kazakhstan, offered ICONICS GENESIS32™ OPC-based HMI/SCADA suite for Kazakhstan’s railway ASCUE. The solution was approved by KTZ’s Energy Supply Department thanks to ICONICS ability to meet the specified project requirements. ICONICS’ GENESIS32 software was selected to replace a competitor’s legacy product. The teamwork of Technik-Trade, KTZ’s Energy Department engineers and managers, the railway division’s ASCUE specialists, the metrological service direction of the Kazakhstan Electricity Grid Operating Company (KEGOC) and the contractors’ staff (from organizations including Transtelecom, Astel, TEP, RECLE and KESH) helped ensure the success of the project.
Read More
The ASCUE system implemented with ICONICS GENESIS32 HMI/SCADA suite helps KTZ cut the cost of electric power purchasing, as well as control all levels of energy consumption.
The project also supports the data exchange between analogous energy accounting control systems.
KTZ and Technik-Trade are working on expanding the system to other KTZ locations and developing a new ASCUE system for South Kazakhstan.
322 substations (including 58 energy nodes and 264 standard substations) that were automated in the project.
Three hundred data acquisition nodes and 9,100 parameters were configured as part of the project.